Water Line, Meter Pit, and Sill Plates Installed - July 22

Forms for footers - June 27

Site Survey - June 13

Breaking Ground - June 10

Water & Sewer Lines Inspected, Backfilled & Crane Pad Ready - July 25

Finally Ready for Set! - July 27

Footers Complete - June 30

Sewer Line and Steel Beam Installed - July 19

Ready for footer forms - June 23

Pouring Foundation Walls - July 12

Foundation Walls Complete - July 13

Excavation Begins - June 15

Waterproofing Foundation Walls - July 14